Drayton Park Golf Course
Wednesday, 11 February 2015
Sunday, 23 March 2014
AGM Course Maintenance Report 2014
We have had
one of the wettest winters in the history of Drayton Park! The course has stood
up to this extremely well, having only had to close for one weekend due to
severe flooding. The greens have continued to play well albeit at times being a
little soft. Last summer work was carried out on the 6th, 7th
and 8th to try and improve the drainage. It does appear this has
been partly successful as following heavy downpours the greens surfaces were
playable more quickly. More work will be required this year to continue this
improvement. The introduction of a storm drain on the 7th hole has
reduced the flooding in this area; standing water was only seen for a very
short time. The verti-draining carried out to all the fairways in September was
the biggest contributing factor in keeping the course playable. There were only
a few isolated areas which became muddy but generally the grass cover remained
good. For this reason I will be planning to get this work completed again this
year.
At the end
of July the 18th fairway was re levelled. The main construction work
was completed within four days, once the grass re-established, the area was
brought back in play.
The area did become muddy
towards the end of February so was put as GUR for a short time.
The next area that will
require levelling is the 17th fairway. This area has sunk and is now
causing a drainage problem. The work will be carried out when conditions allow,
again the work will be completed as quick as possible to minimise the
disruption to play.
This winter
we have continued the policy of thinning out the conifer trees and removing the
lower branches of the pine and deciduous trees. The two poplar trees by the clubhouse
have also been removed; this will stop the roots causing problems to the
surrounding paths and wall and also give a better view of the course from the
clubhouse balcony. Three poplar trees have also been removed from the Pitch and
Putt course. These where already causing a problem to the 6th green
from the ingress of their roots.
The greens are
in good shape with excellent grass cover and have already firmed up. The spring
maintenance program has been started (scarifying and grooming) to remove the
build up of thatch. The first application of sand will soon be applied which
will help to level and smooth out the surface.
Mark Smith
Head Greenkeeper
Monday, 28 October 2013
Golf Course Maintenance Update October 2013
Following a
busy few months I thought it was time to send out a maintenance update.
I have been
pleased with how the greens have responded to all the scarifying and regular
sanding we did throughout the summer. The emphasis was on producing a firmer and
truer putting surface.
Our Autumn
maintenance started during the first week of September. We carried out hollow
coring and sand topdressing to the greens. Once again this went very well.
Recovery was a little slow initially, this was mainly due to lack of rain fall.
The irrigation was used but nothing beats a good shower of rain. The putting
surface did settle down after a couple of weeks with the help of some light
rolling. You may have noticed a few of the hollow core holes staying open. This
was due to the Crane Fly larvae (leather jackets) living in the holes and
coming to the surface to graze on the grass. The greens have now been sprayed
to control these.
Now we are
heading in to November the greens are in excellent condition to take us through
the winter. There have been a couple of days of heavy rain. The greens have
remained reasonable firm and disease free.
During 2012
you will remember that it seemed as if it was never going to stop raining. This
continued into the start of 2013. The golf course continued to play reasonably well
but I had notice the fairways getting wetter and wetter. I suggested to the directors of the golf
course that it would be a good idea to get a contractor in to carry out some
verti-draining which they agreed.
This was
arranged to coincide with the hollow coring during the 1st week of
October. Unfortunately after completing 6 fairways the machine developed a fault.
It was decided that the best course of action was for the contractor to come
back a few weeks later once the machine had been fixed. Upon his return
everything went very smoothly, the rest of the fairways were completed in three
days. The fairways recovered quickly; so far the results have been positive. It
will be interesting to see if there is less standing water this winter!
Work has
been carried out on a few ditches. I will try and get some more done next year
when the ground conditions are suitable for heavy machinery.
Once again I
will be keeping you informed of the work we are doing throughout the winter. We
are looking at investing in some new machinery. Top of the list is a new bunker
bike. I think that this will help us present the bunkers in a better condition,
especially when they are wet.
I hope
everyone visiting the clubhouse have spotted the hard work of one of the
greenkeepers who is improving the appearance of the front entrance. Good work
Mick!
Mark Smith
Head Greenkeeper
Thursday, 15 August 2013
Cleaning out the ditches
We've been working on the cross ditches on the 6th 7th and 8th fairways. it's possible to see the early morning mist in a few pictures. We had a couple of early starts so we could complete the work before play started.
Friday, 2 August 2013
The 18th fairway update
This week we received some much needed rain. This has helped green up the fairways and banks. The newly seeded area on the 18th has germinated. (see pictures)
Please be aware I have found a lot of wasp nests around the course especially on the banks near lakes and streams.
Tuesday, 23 July 2013
Subscribe to:
Posts (Atom)